目前,橋架因其具有美觀、安裝簡單、操作方便等優點,在市場上非常受歡迎。那么你知道在設置和設計
山東橋架時應該明確哪些要點嗎? 以下和小編一起去看以下吧。
At present, the cable tray is very popular in the market because of its beautiful appearance, simple installation and convenient operation. Do you know what points should be made clear when setting and designing Shandong cable tray? Let's go and see the following with Xiao Bian.
1、荷載計算。計算山東橋架在干線縱斷面上的單位長度電纜重量。
1. Load calculation. Calculate the cable weight per unit length of Shandong cable tray on the trunk line profile.
2、繪制橋架平面、剖面圖,部分部位繪制空間圖,制作材料表。
2. Draw the plan and section of the cable tray, draw the space map for some parts, and make the material list.
3、確定橋架方向。根據建筑中平面布置圖,結合空調管路和電氣管路等安裝情況、維護方便、電纜布線疏密確定山東橋架較好路線。
3. Determine the direction of the bridge. According to the layout plan of the building, combined with the installation of air conditioning pipelines and electrical pipelines, convenient maintenance, and cable routing density, a better route of Shandong cable tray is determined.

在室內,應盡量沿建筑物的墻、柱、梁、樓板架設。另外,需要利用綜合回采巷道架設時,需要平行架設在管道的一側或上方。此外,應考慮引下線和分支線盡量不交叉,如未借用其他管道框架,需自行設置柱子。
In the interior, it shall be erected along the wall, column, beam and floor of the building as far as possible. In addition, when it is necessary to use the comprehensive mining roadway for erection, it needs to be erected on one side or above the pipeline in parallel. In addition, it should be considered that the downlead and branch lines should not cross as much as possible. If other pipe frames are not borrowed, columns should be set up by yourself.
4、確定橋的寬度。根據布設電纜數量、電纜直徑及電纜間距確定橋架型號、規格、臂長、立柱長度、間距、橋架寬度和層數。
4. Determines the width of the bridge. Determine the model, specification, arm length, column length, spacing, bridge width and layers of the bridge according to the number of cables laid, cable diameter and cable spacing.
5、確定安裝方法。橋架的適用范圍根據場地設置條件確定橋架的固定方法,選擇懸掛式、直立式、側壁式或混合式,連接件和緊固件通常成套供應,并根據橋架結構選擇合適的蓋板。
5. Determine the installation method. The scope of application of the cable tray shall be determined according to the site setting conditions. Suspension, vertical, side wall or hybrid cable tray shall be selected. Connectors and fasteners are usually supplied in complete sets, and appropriate cover plates shall be selected according to the cable tray structure.
The above five points need to be clarified when installing and designing the bridge. I believe that after reading this content, you will have a further understanding. I hope these contents will be helpful to you. If you want to know more details, please pay attention to the website in time http://www.yeeones.com The dynamics of.