電纜橋架的規格型號和型號規格應合乎當場工程施工環境藝術設計規定,查驗內外應完好無缺,無縫拼接毛邊,不可以發生彎折,折翹這些狀況。
濟南電纜橋架的安裝使用要知道這8點!
The specifications, models, and specifications of the cable tray should comply with the artistic design requirements of the on-site engineering construction environment. The inside and outside should be inspected to ensure that they are intact, seamless splicing of burrs, and no bending or warping are allowed. Jinan cable bridge installation and use to know these 8 points!
1、電纜橋架的較大荷載和支撐點間隔應低于容許荷載和標準支撐點間隔,設備安裝工程中不可載客,如當場自然環境的確需要時,需有安全防范措施設備即可載客,不可讓不過關外行醫生實際操作。
1. The large load and support point spacing of the cable bridge should be lower than the allowable load and standard support point spacing. During equipment installation engineering, it is not allowed to carry passengers. If the natural environment on the spot really requires, safety precautions should be taken to carry passengers. It is not allowed to let unqualified laymen operate.
2、再將表層處理過的立桿,托臂支撐架這些選用膨脹螺絲固定不動在墻壁上(得在混泥土構體和空心磚墻面,不可在空心墻),對當場電焊焊接處搞好防銹解決,當場開展刷涂反腐倡廉漆,電纜橋架敷設時,橋架中間的連接處支點盡可能設定在跨度的1/4上下處。
2. Then, use expansion screws to fix the surface treated upright poles and bracket support frames to the wall (only on concrete structures and hollow brick walls, not on hollow walls). Do a good job in preventing rust at the spot welding joints. Apply anti-corrosive and anti-corrosive paint on the spot. When laying cable bridge frames, the supporting points at the middle of the bridge connection should be set above and below 1/4 of the span as much as possible.
3、針對大跨度橋架較好是擺放在托架上連接,彎通或三通的地區則需獨立提升支點,豎直方位的拖臂每隔1,5米長設一支撐點。
3. For large span bridges, it is better to place them on brackets for connection. For areas with curved or tee joints, it is necessary to independently lift the support points. For vertical trailing arms, support points are set every 1, 5 meters long.

4、橋架內的電纜運用卡帶或是金屬材料電纜卡扣開展固定不動,水準敷設安裝的電纜每隔2米做一個支撐點,豎直敷設安裝的電纜應每隔1-1,5米固定不動一次。
4. The cables in the bridge shall be fixed using a tape or metal material cable clip. For cables laid horizontally and installed, a support point shall be made every 2 meters, and for cables laid vertically and installed, it shall be fixed every 1-1 and 5 meters.
5、不允許穿過墻面及圈梁的橋架與孔眼一起堵死,如果是穿過服務器防火墻及防炎墻體時,應采用防火安全隔離措施。
5. It is not allowed to block bridges and eyelets that pass through walls and ring beams together. If they pass through server firewalls and anti inflammatory walls, fire safety isolation measures should be taken.
6、當工程施工自然環境在戶外豎直安裝橋架時,避免過路人可以多手掀開橋架后蓋板,訂制橋架時要立即跟經銷商反映,對橋架結構加固蝴蝶扣。
6. When installing the bridge vertically outdoors in the natural environment of the project construction, it is necessary to avoid passersby having to lift the rear cover plate of the bridge with multiple hands. When ordering the bridge, it is necessary to immediately report to the dealer and reinforce the butterfly buckle on the bridge structure.
7、當電力工程電纜和操縱電纜很少狀況下,可敷設在同一條橋架上,選用隔開式橋架將不一樣級別電纜分離敷設。
7. When there are few power engineering cables and control cables, they can be laid on the same bridge. Separate bridges are used to separate cables of different levels.
8、假如施工工地是高浸蝕自然環境規定,就可以選用不銹鋼板,鋁合金型材材料橋架。
8. If the construction site is subject to high erosion natural environment regulations, stainless steel plate and aluminum alloy profile materials can be selected for the bridge.
The key points to know about the installation and use of cable trays have been explained to everyone. If you have any doubts or needs about this, please come to our website http://www.yeeones.com Consult and understand!